According to Sina Finance, U.S. affordable housing developers are facing project delays and higher costs under federal domestic-content rules. Avesta Housing abandoned plans to install rooftop solar panels at an apartment building in Conway, New Hampshire, because it could not prove every component met the requirements for using funding from the U.S. Department of Housing and Urban Development (HUD).
Since 2024, more than $68 billion has been subject to the Build America, Buy America rules, equivalent to about 3% of residential construction spending. Public housing agencies say compliance typically raises project costs by 15% to 20%. Congress and then-President Joe Biden expanded the rules to HUD-funded housing projects in 2021. Developers say HUD lacks a fast, standardized process for approving waivers when products are unavailable from U.S. suppliers, and that reviews can take months.
Avesta had planned to install 136 solar panels at a cost of $194,000. Although many components came from the United States, the company could not verify that every part complied, including roof-mounting hardware. The uncertainty and possible fines led it to drop the installation. In Alaska, the Cook Inlet Housing Authority reduced planned six- and nine-unit buildings to four units each to absorb added costs; its vice president, Colleen Dushkin, said Canadian materials are often cheaper and easier to obtain than products shipped from the continental United States.
HUD Secretary Scott Turner cited a May 10 post by President Donald Trump calling for federal agencies to buy U.S.-made goods and opposing waivers. A bipartisan housing bill passed by Congress this summer directs HUD to consult stakeholders, while the department’s inspector general said in a September 10 report that HUD should assign responsibility for enforcing the rules and give staff more authority to act. Some developers want affordable housing projects exempted, citing estimates of a U.S. shortage exceeding 7 million homes. Avesta said it ultimately sourced 97% of the building materials for its New Hampshire project domestically, but warned that sourcing difficulties could affect future projects and delivery schedules.