According to Sina Finance, Turner & Townsend’s latest report found that U.S. data center construction costs rose 13% year over year in 2026, more than twice the global average and about three times the average increase over the past decade.
Demand for large U.S. data centers has surged on the computing needs of artificial intelligence, outpacing the supply of sites with power access and construction workers. The constraints have extended project schedules and increased risks. The report covered more than 500 ongoing or recently completed data center projects across 62 markets and surveyed 400 industry experts worldwide. It said construction-cost inflation had stabilized somewhat but had not offset rapid growth in demand and project delivery activity.
Paul Barry, Turner & Townsend’s head of data center business in North America, said compressed schedules led contractors and subcontractors to include larger risk allowances in bids, covering acceleration, overtime, recruitment incentives and the risks of delivery on unusually tight schedules. He added that surging demand and pressure on supply chains had together raised overall construction costs.
A recent PwC report forecast global data center capital spending would rise from about $800 billion this year to $1.8 trillion annually by 2050. The U.S. is expected to attract nearly half of global investment in AI infrastructure, including data centers and chips.
In Turner & Townsend’s global survey, 56% of respondents cited power supply as a major obstacle to project delivery. Slightly more than half said utility-grid connections typically take one to two years, while nearly one-third said they take more than two years. For a standard 60-megawatt data center design, power costs were $15.01 per watt in Silicon Valley and $10.51 in Dallas. Slightly more than one-quarter of respondents said their contractors had enough capacity to clear their backlogs of ongoing projects.
Barry expects cost growth to ease to 6%–10% next year, saying many large projects have already started or are about to begin and that their contracts have priced in cost risks. He said a large wave of tendering and construction had arrived in 2026, with major projects already accounting for much of the demand.