Hyperscale Data says its Michigan AI data center project will require another $74.8 million from November 2026 through March 2027. According to Odaily, the company said in a regulatory filing that its current funds and available financing are insufficient to cover planned spending and obligations over the next 12 months, raising substantial doubt about its ability to continue as a going concern. At the end of September, the company had $17 million in unrestricted cash and $231 million in current liabilities. Since the end of July, it has sold about 1,113 BTC for proceeds of about $74 million. Construction and equipment costs for the project are estimated at $122.1 million, of which $47.3 million had been paid by October. An agreement with an AI customer has a potential value of up to $1.2 billion, contingent on two customer renewals and the company’s performance.