According to ChainCatcher citing TheMinerMag, Telios Quinlan One LLC, a subsidiary of Bitcoin miner Core Scientific (NASDAQ: CORZ), registered an approximately $1.3 billion data center construction project with Texas regulators on Nov. 13. Construction is planned to begin Nov. 24 in Hunt County, northeast of Dallas. The project includes a roughly 341,000-square-foot data center building, expected to be completed on Sept. 4, 2028.
Core Scientific bought the site for $232.5 million in cash in May this year. AMD has leased 110 megawatts of capacity there, with delivery expected to begin in the first half of 2028. The campus is planned to support up to 285 megawatts of leasable capacity and 430 megawatts of total power capacity. The filing covers one data center building and related site and infrastructure work.
In the third quarter, Core Scientific reported $215.4 million in hosting revenue, about 92% of its $232.9 million in total revenue. The company is scaling back Bitcoin mining and shifting its focus to AI hosting. Billed hosting capacity stood at 485 megawatts as of Sept. 30.